This week’s readings discussed tools that are available for the planning and control of projects. These tools include WBSs, Gantt charts, and PERT/CPM networks. 

In this assignment, you will design CPM and PERT networks to meet the requirements of an engineering firm. The firm needs solutions for the following problem:

One of the firm's existing projects needs to be completed earlier than planned. Use the following data and the critical path and PERT methods to answer the questions that follow. Use the “most likely time” estimate (m) as the time estimate for the CPM analysis.

Activity

Immediate Predecessors

 

Times in Days

 

a

m

b

A

None

1

3

5

B

None

1

2

3

C

A

1

2

3

D

A

2

3

4

E

B

3

4

11

F

C, D

3

4

5

G

D, E

1

4

7

H

F, G

2

4

6

  • Draw the network.
  • Describe the critical path using the CPM approach.
  • Analyze what the estimated completion time using the CPM approach is.
  • Analyze what the estimated completion time using the PERT approach is. 
  • Assess why the estimated completion times are not identical in the two approaches.
  • Under what circumstances would the CPM approach to developing a project plan be more appropriate? Under what circumstances would the PERT approach be more appropriate? 

Submission Details:

  • Submit your report in a three- to four-page Word document, using APA style. 
  • Submit it to the Submissions Area by the due date assigned.
Dot Image
hunnybunn Posted By :
Questions: 1 Tutorials: 0

Click chat button below to get the answer.

Related Questions
You are a new HR Manager who has been hired to work
HR powerpoint You are a new HR Manager who has been hired to work for a manufacturing company called Smith Industrial Operations Products Inc. (SIOP), which employs approximately 350, makes industr …
Change Management - For many companies, change is a constant
Change Management For many companies, change is a constant thing. A company that can smoothly navigate organization change is one that is more nimble and better able to meet market demands for prod …
What do you hope to accomplish with your e-portfolio
What do you hope to accomplish with your e-portfolio? Why and how? Share a brief presentation (PowerPoint, Prezi) of what you have included and intend to include in your e-portfolio.  The present …
MGT555 Unit 5 Discussion - Carl works as a waiter
unit 5 Discussion questions for Employment Law: MGT555 MGT555-2401B-02 Assignment Details Carl works as a waiter for a restaurant in Panama City Beach, Florida. The restaurant closes at 11:00 p. …
HRM533 Discussion - Culture and accountability have recently
HRM533 Discussion Question Culture and accountability have recently been blended within organizations due to fear of change or acceptance of the "that is how we have always done it" menta …
MGT555 Unit 5 Project for Employment Law
unit 5 Project for Employment Law: MGT555 MGT555-2401B-02 Assignment Details In Part 1 of the Personnel Policies and Procedures Manual, you completed the Separation of Employment and Noncompete …
Management - It has been a while since this VP has done anything relative
Management It has been a while since this VP has done anything relative to organizational design, but he has a desire to research the types of design that might help the organization become more cu …
The complexity of WAN’s is increasing every day as new services
Management Advanced Networking Technologies Research Paper Task 2: 1- The complexity of WAN’s is increasing every day as new services and users are exponentially added, the access to the g …
Project management assignment
  Over the past few weeks, we have learned how to develop the project scope, schedule, and cost baselines. While these are useful exercises, it is important for a pro …
Management - What if one person's right to practice
Management Question Book access https://devry.vitalsource.com/#/books/9781264126101?context_token=4da79250-a058-013c-0104-4a72211cd910 Part 1 What if one person's right to practice rel …
Recent Questions
Strayer LEG440 Week 5 Assignment Latest 2024
LEG440 Procurement and Contract Law Week 5 Assignment - Competition Requirements Overview The FAR Parts: Part 15 - Contracting by Negotiation: Subpart 15.2 - Solicitation and Receipt of P …
Strayer LEG440 Week 3 Assignment Latest 2024
LEG440 Procurement and Contract Law Week 3 Assignment - Contracting and the FAR Overview Part of the role of the FAR is to ensure taxpayer funds are properly managed in a way that protect …
Strayer LEG440 Week 4 Activity Case Study: Ethical Considerations Latest 2024
LEG440 Procurement and Contract Law Week 4 Activity - Case Study: Ethical Considerations Preparation Refer to the GSA National Capitol Region 4th Floor Total Workplace Case StudyLinks to an e …
Strayer LEG440 Week 2 Activity Case Study: Acquisition Planning Latest 2024
LEG440 Procurement and Contract Law Week 2 Activity - Case Study: Acquisition Planning Preparation Read the GSA National Capitol Region 4th Floor Total Workplace Case StudyLinks to an ext …
Strayer LEG440 Week 6 Discussion Latest 2024
LEG440 Procurement and Contract Law Week 6 Discussion - After Proposal Submission You are a contracting officer in your agency, tasked with reviewing contractor proposals. What are three …
Strayer LEG440 Week 5 Discussion Latest 2024
LEG440 Procurement and Contract Law Week 5 Discussion  - Price Evaluation You are a contracting officer in your agency, tasked with acquiring office equipment software. After the contrac …
Strayer LEG440 Week 4 Discussion Latest 2024
LEG440 Procurement and Contract Law Week 4 Discussion  - Winning a Government Contract Search the Internet for a news article on government contracting and explain the particular discuss …
Strayer LEG440 Week 3 Discussion Latest 2024
LEG440 Procurement and Contract Law Week 3 Discussion - Fairness of Obtaining a Government Contract Evaluate the level of fairness of the overall process of obtaining a government contract. …
Strayer LEG440 Week 2 Discussion Latest 2024
LEG440 Procurement and Contract Law Week 2 Discussion - The General Services Administration (GSA) Schedule Contract Go to the webpage Acquisition.govLinks to an external site.. Click Brow …
Strayer LEG440 Week 1 Discussion Latest 2024
LEG440 Procurement and Contract Law Week 1 Discussion - Introduction and Government Contracts Introduce yourself to your peers by sharing something unique about your background. Explain how …