MGMT620 week 1 Quiz: Introduction to Project Evaluation/Assessment

Question 1

Which of the following terms is often used to denote a project that a powerful, high-ranking official is advocating?

Sacred cow

Pet project

Political necessity

Special undertaking

Strategic ploy

Question 2

The process of assessing "what we are" and deciding and implementing "what we intend to be and how we are going to get there" is ______________.

strategic management

vision and mission setting

reflection and inquiry

goal and objective clarity

mission assessment

Question 3

Which of the following is NOT one of the traditional components found in mission statements?

Major products and services

Profitability

Target customers and markets

Geographic domain

Contribution to society

Question 4

Organizational objectives set targets for all levels of the organization not just for top management.

true

false

Question 5

When considering criteria used to select projects, capturing a larger market share or reducing the dependency on unreliable suppliers would both be examples of __________ criteria.

Financial

Nonfinancial

Operational

Supplier

Multiple

Question 6

In some cases, organizations will use a(n) __________ to solicit ideas for projects when the knowledge requirements for the project are not available in the organization.

RFQ (Request for Quote)

RFP (Request for Project)

RFP (Request for People)

RFP (Request for Proposal)

Question 7

If a proposed project does not meet one of the designated "must" objectives it should be immediately removed from consideration.

true

false

Question 8

The lack of understanding and consensus of organization strategy among top and middle-level managers is known as the __________.

priority confusion

implementation gap

lack of consensus

lack of comprehension

lack of comprehension and consensus

Question 9

The WBS is best suited for projects that have a tangible outcome. Which of the following is used when the final outcome of the project is less tangible or is a product of a series of steps or phases?

Responsibility matrix

Organization breakdown structure

A work breakdown structure is still effective for these types of projects.

Priority matrix

Process breakdown structure

Question 10

Taking advantage of opportunities to reduce costs or accelerate the schedule are examples of project criteria classified as ____________.

enhanced

accepted

constrained

static

unchangeable

Question 11

The tendency for the project deliverables to expand over time—usually by changing requirements, specifications, and priorities—is called

scope erosion.

scope creep.

project bloat.

scope enhancement.

project add-ons.

Question 12

In regard to project priorities, if a project parameter such as the completion date or the cost of a project is fixed and must be met, it is considered ____________.

enhanced

accepted

constrained

static

unchangeable

Question 13

Which of the following items on the Project Scope Checklist answers the question “What end result is wanted?”

Project objective

Product scope description

Justification

Deliverables

Milestones

Question 14

If a project criterion should be optimized if at all possible, it is classified as being constrained.

true

false

Question 15

A document that is issued by upper management and provides the project manager with written authority to use organizational resources for project activities is called a(n) __________.

project charter

statement of work

requirements document

project plan

scope statement

Question 16

The WBS is best suited for design and construction projects that have tangible outcomes. When the final outcome of the project is less tangible or it is the result of a series of steps or phases, some project managers choose to utilize a(n) ___________.

Work Breakdown Structure (WBS) Modified

 Process Breakdown Structure (PBS)

Organization Breakdown Structure (OBS)

Project Priority Matrix (PPM)

Responsibility Matrix (RM)

Question 17

A key aspect to communication plans are that they allow the project manager and the project team to

meet deadlines more effectively.

focus on defect resolution.

effectively control costs on the project.

actively control the flow of information.

be more creative in their communications.

Question 18

Research indicates that high-performance project teams are much more likely to develop under certain conditions. One of these conditions is that members are assigned to the project _______ time.

part

full

split

over

by ending

Question 19

When a project manager intervenes and tries to negotiate a resolution by using reasoning and persuasion and suggesting alternatives, he or she is ___________ the conflict.

mediating

arbitrating

controlling

accepting

eliminating

Question 20

Project managers should manage ___________ conflict.

functional

dysfunctional

creative

diverse

emotional

Question 21

During which stage of team development do team members establish ground rules and try to find out what behaviors are acceptable and what performance expectations are?

Norming

Storming

Performing

Adjourning

Forming

Question 22

An image a project team holds in common about how the project will look upon completion, how they will work together, and/or how customers will accept the project is known as a __________. It is a less tangible aspect of project performance.

vision

identity

characteristic

ritual

discipline

Question 23

When project managers impose a solution to dysfunctional conflict after listening to each party, they are __________ the conflict.

eliminating

controlling

mediating

arbitrating

encouraging

Question 24

When reaching a decision during the group decision-making process, the project manager must build a consensus among the group and can do this by all of the following EXCEPT

if time becomes a factor, they must make an informed final decision after everyone's ideas have been heard.

provide periodic summaries to help the group keep track of its progress.

protect those members who represent the minority view.

guarantee that everyone has the opportunity to share opinions.

manage any conflict that may arise.

Question 25

Every project has the same potential to evolve into a high-performance team.

true

false

 

Dot Image
Getsolution Posted By :
Questions: 14947 Tutorials: 14946
Tutorials for this Question

MGMT620 Week 1 Quiz Latest 2024

Tutorial # 00652031
Posted On: 05/16/2024 03:13 AM
Feedback Score: Not rated yet!
Purchased By: 2
Getsolution
Posted By:
Questions:
14947
Tutorials:
14946
Report this Tutorial as Inappropriate
Tutorial Preview
The solution of MGMT620 Week 1 Quiz Latest 2024...
Attachments
MGMT620_Week_1_Quiz_Latest_2024.docx (140.21 KB)

Great! We have found the solution of this question!

Related Questions
Business Process Management - Paradigms in Business Process Management
BUSINESS PROCESS MANAGEMENT To prepare: Read the article, “Paradigms in Business Process Management Specifications: A Critical Review.” Pay particular attention to the descriptions o …
MGMT620 Week 1 Quiz Latest 2024
MGMT620 week 1 Quiz: Introduction to Project Evaluation/Assessment Question 1 Which of the following terms is often used to denote a project that a powerful, high-ranking official is advocating? …
MAN671 - Compare and contrast three leaders
MAN671 Business Question Compare and contrast three leaders from any industry that possess charismatic and transformational leadership qualities. Explain the degree of ethics, diversity, and …
HRM538 Week 1 Discussion
HRM538: Week One Discussion Question this Crucial Learning video may help you respond to the questions that follow: Awkward Performance Review [Video]Links to an external site.. (2 mins, 38 s …
MGT323 Assignment 3 Project Management
MGT323 Business Question Assignment 3 Project Management (MGT 323) The Assignment must be submitted on Blackboard (WORD format only) via allocated folder. Assignments submitted through ema …
You are a new HR Manager who has been hired to work
HR powerpoint You are a new HR Manager who has been hired to work for a manufacturing company called Smith Industrial Operations Products Inc. (SIOP), which employs approximately 350, makes industr …
Change Management - For many companies, change is a constant
Change Management For many companies, change is a constant thing. A company that can smoothly navigate organization change is one that is more nimble and better able to meet market demands for prod …
What do you hope to accomplish with your e-portfolio
What do you hope to accomplish with your e-portfolio? Why and how? Share a brief presentation (PowerPoint, Prezi) of what you have included and intend to include in your e-portfolio.  The present …
MGT555 Unit 5 Discussion - Carl works as a waiter
unit 5 Discussion questions for Employment Law: MGT555 MGT555-2401B-02 Assignment Details Carl works as a waiter for a restaurant in Panama City Beach, Florida. The restaurant closes at 11:00 p. …
HRM533 Discussion - Culture and accountability have recently
HRM533 Discussion Question Culture and accountability have recently been blended within organizations due to fear of change or acceptance of the "that is how we have always done it" menta …
Recent Questions
Walden HLTH5205/HLTH6205/HLTH8205E All Assignments Latest 2024
HLTH-5205-1/HLTH-6205-1/HLTH-8205E Assessing Community Needs-Summer 2024 Week 2 Assignment SWOT ANALYSIS A SWOT analysis is a tool used in gathering and identifying assets and resources of a …
Walden HLTH5205/HLTH6205/HLTH8205E Week 10 Assignment Latest 2024
HLTH-5205-1/HLTH-6205-1/HLTH-8205E Assessing Community Needs-Summer 2024 Week 10 Assignment PROPOSAL FOR CHANGE Social change remains at the center of what health educators seek to accomplish …
Walden HLTH5205/HLTH6205/HLTH8205E Week 8 Assignment Latest 2024
HLTH-5205-1/HLTH-6205-1/HLTH-8205E Assessing Community Needs-Summer 2024 Week 8 Assignment UNDERSTANDING THE ROLE OF INFORMATION DISSEMINATION AND THE USE OF DIGITAL TECHNOLOGY Regardless of …
Walden HLTH5205/HLTH6205/HLTH8205E Week 6 Assignment Latest 2024
HLTH-5205-1/HLTH-6205-1/HLTH-8205E Assessing Community Needs-Summer 2024 Week 6 Assignment DATA COLLECTION MEASURES Data collections methods for community health needs assessment include qua …
Walden HLTH5205/HLTH6205/HLTH8205E Week 3 Assignment 2 Latest 2024
HLTH-5205-1/HLTH-6205-1/HLTH-8205E Assessing Community Needs-Summer 2024 Week 3 Assignment 2 COMMUNITY HEALTH NEEDS ASSESSMENT  A community health needs assessment involves a number of …
Walden HLTH5205/HLTH6205/HLTH8205E Week 3 Assignment 1 Latest 2024
HLTH-5205-1/HLTH-6205-1/HLTH-8205E Assessing Community Needs-Summer 2024 Week 3 Assignment 1 WALKING OR WINDSHIELD SURVEY Walking surveys are systematic observations made while walking throug …
Walden HLTH5205/HLTH6205/HLTH8205E Week 2 Assignment Latest 2024
HLTH-5205-1/HLTH-6205-1/HLTH-8205E Assessing Community Needs-Summer 2024 Week 2 Assignment SWOT ANALYSIS A SWOT analysis is a tool used in gathering and identifying assets and resources of a …
Walden HLTH5205/HLTH6205/HLTH8205E All Discussions Latest 2024
HLTH-5205-1/HLTH-6205-1/HLTH-8205E Assessing Community Needs-Summer 2024 Week 1 Discussion ASSESSING COMMUNITY NEEDS This Discussion will be available from Day 1 through Day 7 of this week. Y …
Walden HLTH5205/HLTH6205/HLTH8205E Week 11 Discussion Latest 2024
HLTH-5205-1/HLTH-6205-1/HLTH-8205E Assessing Community Needs-Summer 2024 Week 11 Discussion HEALTH EFFECTS ON THE BUILT ENVIRONMENT This Discussion will be available from Day 1 through Day 7 …
Walden HLTH5205/HLTH6205/HLTH8205E Week 10 Discussion Latest 2024
HLTH-5205-1/HLTH-6205-1/HLTH-8205E Assessing Community Needs-Summer 2024 Week 10 Discussion COMMUNITY ACTION PLANS–APPLYING THE NEEDS ASSESSMENT This Discussion will be available from D …